Enabling Row Drag And Drop


You can turn on drag and drop of rows in the FlexyGantt's FlexyTable as follows:


       public MainPage()

        {

            InitializeComponent();

            this.fxgantt.FlexyTableCreated += new EventHandler(fxgantt_FlexyTableCreated);

        }


        void fxgantt_FlexyTableCreated(object sender, EventArgs e)

        {

            // Turns on dragging rows

            this.fxgantt.FlexyTable.CanUserReorderRows = true;


            // Allows dropping as a child of another row.

            this.fxgantt.FlexyTable.EnableDropAsChild = true;


            // Event that gets called when a row is dropped over another.

            this.fxgantt.FlexyTable.SelectedRowsDrop += newRadiantQ.Windows.Controls.Gantt.SelectedRowsDropEventHandler(FlexyTable_SelectedRowsDrop);

        }


This will allow you to start dragging rows:

Dragging a FlexyGantt row


Next, listen to drop events as follows:


     void FlexyTable_SelectedRowsDrop(object sender, RadiantQ.Windows.Controls.Gantt.SelectedRowsDropEventArgs args)

        {

            // Here the args will give you the rows that are being dragged and the destination row, including whether the user wanted the rows to be dropped as sibling or children.

        }


A sample that illustrates this feature can be located here in the install:

..\Samples\FlexyGantt\User Interaction\MovingResourceRows.